TRAFFIC ADVISORY- MORGAN STREET WATER MAIN PROJECT

Posted on Oct 02 2011
Press Releases >>

October 3, 2011

TRAFFIC ADVISORY FOR MORGAN STREET WATER MAIN PROJECT

 

Residents and commuters are advised that the upcoming construction project of the Morgan Street Water Main will have an impact on traffic on the road. The installation of environmental controls is scheduled to begin on or about September 29th.   Mobilization and delivery of construction materials is scheduled to begin during the week of October 3rd

Installation of the water main is scheduled to commence during the week of October 10th and will begin in the vicinity of #31 Morgan Street and proceed south on Morgan Street towards the intersection of Morgan Street and New Ludlow Road.  Morgan Street will be closed to thru traffic during construction hours; however, emergency and school bus traffic will be maintained as usual.

Last changed: Oct 03 2011 at 12:51 PM